Using the resource library
Goal: use resources from the resource library in your project, and put a resource that you made in a project into the library, so that every project uses the same data.
You have a fixed bricklaying crew, a crane and a plasterer who appear in several projects. Without a library you type them in again in every project, with a risk of different names and rates, and no project sees that another one asks for the same crew as well. In the library you record them once.
What the library is and what a project takes over from it, you read in The resource library. This article is about the actions. Creating, exporting and deleting libraries is in Managing and sharing resource libraries.
You only work with the library if the project is linked to it. Without a link, the Resources panel does not show the Library, Project and Occupancy switch.
For a new project:
- Choose File › New. The New project window opens.
- Look at Resource library. The field is set to the default library. You can choose another one, none (standalone project) or + New resource library….
- Click Create.
For an existing project:
- Choose File › Project settings.
- Under Resource library, choose the library.
- Click Apply. Until then the bottom says Changes not applied — click Apply to keep them.
If the project already has resources with the same name as a library item, the Link resource library window opens with the section Recognized. Each resource with a match says Suggested: Bricklayer. Click Link to link that one, or Link all suggestions if there is more than one suggestion. The app compares names without regard to capital letters or double spaces. When linking, the resource takes over name, type, rate, unit and description from the library item. Max units stays what you had in the project. The window also shows calendars of the project that have the same name as a library calendar. With Decide later you close the window without linking.
- Choose Resources › Manage › Resources. The resource panel takes over the workspace. It always opens on Project, also for a linked project.
- At the top right, choose Library. Above the table it says This edits the library and applies to all projects — outside undo.
- Click New resource in library. An empty row appears at the bottom of the table.
- Type the name, for example Bricklayer, and press Enter. The resource is now in the library and an empty row opens straight away for the next one. Press Esc when you are done. Without a name the app creates nothing.
- Fill in the rest of the row. Type is Labor by default. Under Max units you enter how many of this resource there are in total, for example 3 for three bricklayers. The occupancy overview uses this number as capacity. Rate/hour is optional. You can only fill in Unit for the type Material. Under Calendar you choose a calendar from the library, or + Resource calendar to make one, see Setting up a resource calendar. The app stores name, rate and unit when you leave the field, and the other fields straight away.
Every change in the library immediately works through into the unedited copies in your open projects.
- In the Library view, choose Assign to project on the resource. Above the table it says Added. If you click again, it says Already in the project. and no second copy appears.
- Choose Project. The copy is in the table with a small library icon next to the name, called From the library. Name, type, rate and unit are plain text. If you hold the mouse over them, you see Library value — edit it in the Library view, or unlink this resource from the library.
- Set Max units for this project. The field starts with the value from the library and stays editable in the project.
- Now assign the resource to tasks like any other resource, see Assigning resources with a curve. Resources › Assignment › Assign only shows resources that are already in the project, so first assign a library resource to the project in this way.
Assign to project only exists in the Library view of a project that is linked to that library.
You do this for a resource that you made in the project and use more often, such as a hired crane.
- In the Project view, choose To the library on the resource. The button only appears on a resource that has a name and does not yet come from the library, in a linked project.
- Read the message above the table.
The message can say three things:
- Added. The library had no item with that name. A new item was made and your resource is linked to it.
- Already existed in the library — now linked. There was an item with the same name and the same data. Your resource is linked to it.
- Linked to the existing library item — the values differ, see the marker. There was an item with the same name but different data. Your resource is linked and is immediately marked differs — decide. Continue at step 6.
If you want to deviate from the library in one project, for example with a different rate, you unlink the copy.
- In the Project view, click the icon Unlink from library at the end of the row.
- The resource is now an ordinary project resource. All fields are editable and it no longer follows the library. The calendar that came along with the resource is unlinked too, unless another resource in this project still follows it.
With Undo (Ctrl+Z) you take the unlinking back.
A copy that says differs — decide differs from the library item. The app does not choose who is right.
- Click the marker differs — decide on the resource. The Link resource library window opens. It also opens by itself when you open a file with such a copy.
- In the section Deviations, choose what you want for the item, see below.
- Click Decide later if you do not want to choose yet. The window closes and the marker stays.
For a deviation you have two choices:
- Use library values: the copy gets the data from the library.
- Adopt file values into the library: the library gets the data from your copy. Below it says Note: this changes the library and applies to all your projects. The copies in other open projects follow.
The example projects have a library of their own. If you open one of the three showcase examples (File › Examples, or through a link in Help), the app once creates the library Demo resource library and links the project to it. Resources of the project with the same name as a library item are linked straight away; calendars are not. Your own libraries are left alone. If you open two showcases side by side, together they show conflicts in Using the occupancy overview, for example on the masonry crew (Masonry crew) between Refurbishment & Extension of a Family Home and 6 New Terraced Houses, De Akkers.
You do not see the switch. The project is not linked to a library. Do step 1.
You edit the library by accident. The panel always opens on Project to prevent that. Changes in the Library view apply to all projects and fall outside Undo.
You delete a resource from the library. The app first asks Remove 'Bricklayer' from the library? This applies to all projects and cannot be undone. The copies in your projects stay and keep working. They get the marker no longer in the library and are fully editable. With Remove from project you take a copy out of the project.
Under Resource library you choose another library or none (standalone project). The origin stamps of the previous library disappear. The resources stay in the project as ordinary project resources. With another library, the app looks again for resources with the same name.
A resource has no suggestion in Recognized. It says No suggestion — choose manually, but this window has no button for that. That looks like a shortcoming. Put such a resource in the library with To the library (step 4).
- The resource library: what the library decides, what the project decides, and how copies follow along.
- Managing and sharing resource libraries: creating, exporting and importing libraries.
- Using the occupancy overview: seeing whether two projects ask for the same resource at once.
- Managing resources: the resources of a single project.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project