Creating a hammock
Goal: create a task that does not know its own duration, but runs from the start of one task to the finish of another, such as site setup, supervision or the hire of a site cabin.
The site cabin stands there for as long as the building goes on, from the first groundwork to the handover. If you give that task a fixed duration of 13 work days, it does not follow along when the brickwork runs late, and the schedule stops being right. A hammock (also called level of effort) follows the work you hang it on: its start comes from a start relation, its finish from a finish relation, and its duration is the difference between the two.
- Create the task, for example Site cabin, or select an existing task. A milestone and a summary task (phase) cannot be a hammock; in the Properties panel and in Edit task the tick box is missing for such a task, and in the table column it cannot be changed.
- Tick Hammock (derived duration) in the Properties panel, in Edit task (right-click the task, Edit...) or in the table column Hammock (derived duration) under Planning. The Duration field can then no longer be edited.
- Add a relation from the task the hammock starts with to the hammock, of type SS (the hammock starts together with that task) or FS (the hammock starts after that task). To do so, select the hammock, click Add relation in Dependencies, leave the direction on Predecessor, choose the task and choose the type. The steps are in Adding relations.
- Add a relation from the task the hammock ends with to the hammock, of type FF (the hammock finishes together with that task) or SF.
- Look in the Properties panel under Hammock (derived duration): there you see Start driver with the task and the type, and Finish driver with the task and the type. A driver is a task the hammock takes its start or finish from.
- Press Calculate (F5), for example through Home › Schedule › Calculate. The hammock now runs from the start of the start driver to the finish of the finish driver, and Duration shows the derived duration.
In the Gantt a hammock is a thin teal bar with a hook at both ends.
Example: Site cabin gets SS from Groundwork (Monday 7 June 2027) and FF from Roofing (done Wednesday 23 June). After Calculate the hammock runs from Monday 7 to Wednesday 23 June: 13 work days. If the brickwork runs 2 work days late, the end of Roofing becomes Friday 25 June and the hammock grows along to 15 work days.
- The hammock is never critical and has no float. It does not restrict the tasks it takes its start and finish from either: they get no late date because of the hammock.
- A lag counts. With SS and lag
1dthe hammock starts a work day after the start driver, with FF and lag2dit finishes two work days after the finish driver.
No finish driver. If the hammock has no FF or SF relation, the app cannot derive its finish. The Properties panel says No finish driver (FF/SF) — the span falls back to zero length. and the Warnings panel says Hammock without a finish driver (no FF/SF predecessor): its duration falls back to zero. The hammock then starts and finishes on the same day. Add an FF or SF relation.
A hammock that finishes after the last task. If the hammock carries on until after the last task, for example with FF and a lag of 2 work days, the finish date of the project moves along. The tasks you really carry out then get float; none of them is critical any more.
Tasks that wait for a hammock. If you add a relation from the hammock to another task, that task only starts after the end of the hammock. The whole chain before the hammock, including the tasks the hammock takes its start and finish from, then gets float and is no longer critical, because the hammock gives no pressure back. So do not let tasks wait for a hammock; rather hang such tasks on the hammock's finish driver.
Entering a duration. The Duration field of a hammock is derived and cannot be edited. A duration you had entered before ticking the box no longer counts.
- Adding relations: the steps to add a relation of type SS or FF.
- Relations and lag: what SS and FF mean and how the lag counts.
- Critical path and float: what critical means and how float works.
- De Vaart Apartment Complex: contains the hammock Structural works tower A (LOE).
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an MCP client
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the MCP link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- MCP tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project