Turning on hour planning
Goal: plan tasks in working hours, alongside tasks in days.
You hire a crane by the hour, not by the day. A pour of six hours does not fit in a whole work day. A night crew works at different times from the day crew. For such work you want a duration in hours and a start and finish with a clock time. You also turn this on if you open a file and the app reports This file contains hour-based planning. Why the app counts days and hours differently, you can read in Days and hours.
- Choose Settings › Project › App settings and open the Planning tab.
- Under Hour planning, tick Enable hour planning. It works right away. In the message This file contains hour-based planning. the Enable hour planning button does the same.
- Below it is Allow mixed day/hour planning, on by default. With that setting you choose per task whether it counts in days or hours. If you turn it off, the Duration unit list disappears. You can then still type a duration with a unit, such as
12h.
That changes more than the duration of a task: under View › Time Scale you can choose the scale Hour, in the Calendars window an ordinary calendar can get working-time blocks (the Working times block; a calendar that already has blocks always shows it), and the New project window gets the choices Shift and Default unit for new tasks.
- Select the task and look in the Properties panel, under Time, at the Duration field.
- Type the duration with a unit and press Enter:
12h(12u, the Dutch abbreviation, also works) for twelve hours,1h 30mfor an hour and a half.1.5his fine too. A number without a unit counts in the unit the task already has. - If you want to convert an existing task, choose the unit Hours under Duration unit. The app converts the duration immediately, for example from
2days to16hours. To go back, use Undo. - Back to days is possible with
2dor with the unit Days. - Press Calculate (F5), for example via Home › Schedule › Calculate. The task now has a start and finish with a clock time.
- If you want to see the hours in the Gantt, choose the scale Hour in the list under View › Time Scale.
- Choose Settings › Project › Project settings.
- Under Default unit for new tasks, choose the unit Hours and click Apply.
A new task then starts with 5 hours instead of 5 days. Existing tasks do not change. With a new project the same choice is in the New project window. If you choose Day shift under Shift there, Hours is disabled. Choose another shift, or set the default unit after creating in Project settings.
No valid working times. If the task's calendar has no usable working times, the app reports This calendar has no valid working times. Check its working days and times. When calculating, the message Hour task 'name' has no valid working hours in its calendar can appear.
No decimals with days. A duration in days is a whole number. 1.5d gives the message Enter a whole number of days or hours, for example 2d or 12h. If you want a day and a half, calculate in hours.
A conversion that cannot be exact. Twelve hours does not fit in whole days of 8 hours. In Properties and in Edit task the app then shows a yellow block with 12h does not fit into whole days on this calendar. The unit has not changed. and leaves the unit. The task table gives a shorter message: This duration cannot be converted to the other unit exactly.
The field is disabled. For a phase, a hammock or a milestone with zero duration the duration follows from something else, and you cannot type it.
Turning hour planning off again. Tasks in hours remain and are still calculated. Their duration cannot be edited then; the field says Enable hour planning to edit this hour task., with a button to turn it on again.
- Days and hours: how the app counts hours, what happens when days and hours meet and where it rounds.
- Setting working times: the times of a calendar per weekday.
- Adding relations: a lag in hours between two tasks.
- App settings: the setting Enable hour planning and what else it changes.
- De Vaart Apartment Complex: contains tasks in hours (rebar fixing and pouring) with an hour calendar of its own, Hourly calendar, rebar fixing & pouring.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Tutorials
Step-by-step tutorials live in the app: install the Tutorials extension via Help › Tutorials.
How-to guides
- Adding relations
- Adding tasks and milestones
- Adjusting the structure
- Saving and inserting WBS templates
- Codes and custom fields
- Splitting a task
- Moving a project
- Selecting, deleting and undoing tasks
- Tracing a path
- External relations to another project
- Setting a constraint or deadline
- Creating a hammock
- Creating and assigning a calendar
- Generating holidays and the construction holiday
- Setting up a resource calendar
- Turning on hour planning
- Setting working times
- Managing resources
- Assigning resources with a curve
- Adjusting the hour distribution
- Choosing a task type
- Resolving overallocation
- Choosing or building a calculation profile
- Saving and managing a baseline
- Updating progress
- Importing progress from a spreadsheet
- Choosing the progress mode
- Making and printing a report
- Choosing the reporting period
- Creating and using a layout
- Adjusting table columns
- Using split view and the mini-map
- Dragging, panning and zooming in the Gantt
- Presenting on a large screen
- Working with several projects at once
- Opening and saving a file
- Turning on AutoSave
- Opening an MS Project file (.mpp)
- Opening a Primavera P6 file (.xer)
- Exporting
- Choosing the IFC schema
- Recovering after a crash
- Using the resource library
- Managing and sharing resource libraries
- Using the occupancy overview
- Installing and managing an extension
- Connecting an AI assistant (MCP)
- Giving feedback
- Updating the app
Explanation
- Planning well
- Critical path and float
- Relations and lag
- Constraints and deadlines
- Calendars and working days
- Days and hours
- Task types: duration, units and work
- Resource leveling
- Progress, status date and baseline
- Calculation profiles and conventions
- Files and formats
- Dates as recorded
- The resource library
- How the AI link works
Reference
- The ribbon, tab by tab
- Task dialog and properties panel
- Calendar windows
- Resource panel
- Table columns
- Notifications and warnings
- AI tools (planner_*)
- Keyboard shortcuts
- Right-click menus
- App settings
- New project and Project settings
- Calculation options and conventions
- Import and export formats
- Report types
- Extension permissions
Project