Schedule and lead times

The items with the longest lead times are usually:

  • optical table: usually 8 weeks
  • lasers / multiline laser combiners: usually 8-10 weeks
  • PI stages: 8-10 weeks
  • galvo scanners (for non-Thorlabs scanners, e.g. from scanlab): 8 weeks

Therefore, lead times of 10 weeks should be expected.