Project Tasks

Project tasks are work items that need to be tracked. They are different then issues in that items listed here simply need to be completed and are not necessarily risks to the project.

Kick off

| ID | Name | Description | Status | Assigned | Notes | | --- | --- | --- | --- | --- | --- | --- | | K1 | Initial Project Meeting | Meeting of the proposed team members to create objectives, plan for the initial project plan. | done | All Team Members | | | | K2 | Identify the Objectives of the Project | Create a detail project Objective to be achieved for the project including including Timeline and resources. | done | All Team Members | | | | K3 | Tools and Processes | Identify the tools and processes to be used through the project -- these tools include -- dev, test, track, plan, communication | done | All Team Members | performance testing tools -- still open | | K4 | Team | Identify the various roles in the project and assign potential members for the same | done | All Team Members | | |

Planning/Analysis

TimeLine: Begin: Jan 2009 End: 13th Feb 2009

| ID | Name | Description | Status | Assigned | Start Date | End Date | Dependency | Notes | | --- | --- | --- | --- | --- | --- | --- | --- | --- | --- | | P1 | Project Plan | Create the detailed project plan along with Tasks, Timelines and resources. | done | George W | | 9th Feb | | on the development front we are good -- the Testing front we need more support | | P2 | Development Technical Approach | Create the technical approach over all architecture for executing the project. | done | Bruce M/Gurjeet | | 13th Feb | | most of it is identified and the piece open is a set of function we need to port from Oracle | | P3 | Test Technical Approach | Create the technical approach for Testing the application which includes -- functional, regression, performance, migrations and upgrades | in progress | George W/Vikram | | 13th Feb | | need access and support from the Test Team | | P4 | Oracle Sample Database | Creation of the sample database in Oracle for all related activities - including testing for migration, upgrades, functional and performance tests | done | Jeff O | | 13th Feb | | Small DB delivered 1/7. DDL, Sample data available. | | P5 | Reviews of Project plan and technical approach documents | Review the plan and the approaches with the whole team and get approvals | done | Jeff O | | 13th Feb | | | | | P6 | Sign-Off | Sign-off on the above iteration | done | Todd S/Jeff O | | 13th Feb | | | | | P7 | Review next Iteration Plan | Review the plan for the next iteration including tasks, timelines | done | Todd S/Jeff O | | 13th Feb | | | |

Iteration 1

TimeLine: Begin: Jan 2009 - End: 27 Feb 2009

ID Name Description Status Assigned Start Date End Date Dependency Notes
I1 Application Knowledge Transfer A total overview of the complete application -- 1 day for total over view of the application. Half day on functional walk through and half day schema review. done Jeff O 13th Feb Shooting for week of 1/26.
I2 Development Environment Recommend the development environment. done Jeff O 6th Feb EDB team Installed on CENTOS 5. All issues resolved 1/21.
I3 Test Environment Recommend the required environment for the Test Lab in progress Jeff O 13th Feb need time with the Test Team
I4 Setup The Development Environment Setup the development environments done Team 6th Feb see I2.
I5 Setup The Test Lab Setup the Test Environment in progress Tushar/Vikram 20th Feb access to the Test Team
I6 Identify Modules Identify modules and prioritize them done Todd S/Jeff O 13th Feb modules identified - in iteration 2, breakdown
I7 Postgres Schema Generation Create the whole schema for the application 100% 20th Feb process approved: now in converting tables
I8 IMake Files Creation of make files for schema generation in progress done 20th Feb the approach has been identified and first iteration in place
I9 Orafce Testing Identify Orafce usages and short comings and find all the required functionality done Tushar/Vikram 20th Feb identified a set of bugs -- working with the Orafce team on fixes as well as identified a set of features not available -- creating them
I10 Database Access Layer Identify mechanism to effectively to connect to the DB from the application in progress dgoodwin 20th Feb
I11 Packaging Plan Identify the packaging needs of the application in progress dgoodwin 26th Feb
I112 Review next Iteration Plan Review the plan for the next iteration including tasks, timelines Todd S/Jeff O 27th Feb

Iteration 2

TimeLine: Begin: 2nd March 2009 - End: 30th April 2009

ID Name Description Status Assigned Start Date End Date Dependency Notes
M1 Code Merge Merge code with Head and resolve conflicts. Jeff O 6th March
I1 Modules Freeze Identify and freeze the set of modules we are going to work on for this iteration. in progress Jeff O 6th March
I2 Modules Knowledge Transfer Modules Knowledge Transfer and detailed Q&A. Jeff O 14th March
D1 Development: Schema Verification Verify the schema in Pg for the identified modules. schema - 100%, views - 100%, triggers - 100% Gurjeet/Vikram 14th March
D2 Development: Query Identification Identify the queries and validate them. Queries - tagged 100% Gurjeet/Vikram 21st March
D3 Development: Stored functions/procedures/packages Identify all the stored functions/packages/procedures .. and validate them. done Gurjeet/Vikram 21st March
D4 Development: Make the appropriate code Changes Develop all the required code and validate them. Procedures - 100%, Packages - 100% Gurjeet/Vikram 10th April
D5 Development: Oracle to Postgres Migration Generate the Oracle to Postgres Migration script. Farrukh 20th March
D5 Development: Postgres to Oracle Migration Generate the Postgres to Oracle Migration script. Farrukh 17th April
T1 Testing: Test Case Review Review the existing Test cases for the modules. Tushar/Vikram 14th March
T2 Testing: Identify Gaps Identify the gaps in the test cases Tushar/Vikram 14th March
T3 Testing: Develop Test Cases Develop the test cases for the identified gaps. Tushar/Vikram 27th March
T4 Testing: Review Review the existing Test cases for the modules after adding the new ones. Jeff O 3rd April
T5 Testing: Build Automated Test Cases Build and run the complete automated test suite. Tushar/Vikram 24th April
T6 Testing: Oracle to Postgres Migration Test the Oracle to Postgres Migration. Tushar/Vikram 10th April
T7 Testing: Establish Oracle Performance Benchmarks Execute and Establish the Oracle Benchmarks for the application. Tushar/Vikram/Jeff O 10th April
T6 Testing: Postgres to Oracle Migration Test the Postgres to Oracle Migration. Tushar/Vikram 24th April
I3 Review & Sign-off above milestones Review and Sign-off on the above tasks. Todd S/Jeff O 29th April
I4 Review next Iteration Plan Review the plan for the next iteration including tasks, timelines Todd S/Jeff O 29th April

Iteration 3

TimeLine: Begin: 1st May 2009 - End: 29th May 2009

ID Name Description Status Assigned Start Date End Date Dependency Notes
M1 Code Merge Merge code with Head and resolve conflicts. Jeff O 1st May
I1 Modules Freeze Identify and freeze the set of modules we are going to work on for this iteration. Jeff O 1st May
I2 Modules Knowledge Transfer Modules Knowledge Transfer and detailed Q&A. Jeff O 8th May
D1 Development: Schema Verification Verify the schema in Pg for the identified modules. schema - 100%, views - 100%, triggers - 100% Gurjeet/Vikram 8th May
D2 Development: Query Identification Identify the queries and validate them. Gurjeet/Vikram Queries Tagged - 100% 8th May
D3 Development: Stored functions/procedures/packages Identify all the stored functions/packages/procedures .. and validate them. Procedures - 100%, Packages - 100% Gurjeet/Vikram 8th May
D4 Development: Make the appropriate code Changes Develop all the required code and validate them. Procedures - 100%, Packages - 50% Gurjeet/Vikram 22nd May
D5 ?? Development: Upgrade Scripts between versions of Spacewalk Generate the Pg plan/upgrade script for the application. Farrukh 22nd May
T1 Testing: Test Case Review Review the existing Test cases for the modules. Tushar/Vikram 8th May
T2 Testing: Identify Gaps Identify the gaps in the test cases Tushar/Vikram 8th May
T3 Testing: Develop Test Cases Develop the test cases for the identified gaps. Tushar/Vikram 15th May
T4 Testing: Review Review the existing Test cases for the modules after adding the new ones. Jeff O 22nd May
T5 Testing: Build Automated Test Cases Build and run the complete automated test suite. Tushar/Vikram 22nd May
T6 ?? Testing: Upgrade Scripts between versions of Sapcewalk Test the upgrade scripts migration. Tushar/Vikram 28th May
T7 Testing: Establish Pg Performance Benchmarks Execute and Establish the Pg Performance Benchmarks for the developed modules. Tushar/Vikram/Jeff O 28th May
I3 Review & Sign-off above milestones Review and Sign-off on the above tasks. Todd S/Jeff O 29th May
I4 Review next Iteration Plan Review the plan for the next iteration including tasks, timelines Todd S/Jeff O 29th May

Iteration 4

TimeLine: Begin: 1st June 2009 - End: 30th June 2009

ID Name Description Status Assigned Start Date End Date Dependency Notes
M1 Code Merge Merge code with Head and resolve conflicts. Jeff O 3rd June
I1 Modules Freeze Identify and freeze the set of modules we are going to work on for this iteration. Jeff O 5th June
I2 Modules Knowledge Transfer Modules Knowledge Transfer and detailed Q&A. Jeff O 5th June
D1 Development: Schema Verification Verify the schema in Pg for the identified modules. Schema - 100%, Views - 100%, Triggers - 100% Gurjeet/Vikram 5th June
D2 Development: Query Identification Identify the queries and validate them. Queries Tagged - 0% Gurjeet/Vikram 5th June
D3 Development: Stored functions/procedures/packages Identify all the stored functions/packages/procedures .. and validate them. Procedures - 100%, Packages - 100% Gurjeet/Vikram 5th June
D4 Development: Make the appropriate code Changes Develop all the required code and validate them. Procedures - 100%, Packages - 50% Gurjeet/Vikram 19th June
T1 Testing: Test Case Review Review the existing Test cases for the modules. Tushar/Vikram 5th June
T2 Testing: Identify Gaps Identify the gaps in the test cases Tushar/Vikram 5th June
T3 Testing: Develop Test Cases Develop the test cases for the identified gaps. Tushar/Vikram 12th June
T4 Testing: Review Review the existing Test cases for the modules after adding the new ones. Jeff O 19th June
T5 Testing: Build Automated Test Cases Build and run the complete automated test suite. Tushar/Vikram 26th June
T6 Testing: Establish Pg Performance Benchmarks Execute and Establish the Pg Performance Benchmarks for the developed modules. Tushar/Vikram/Jeff O 26th June
I3 Identify Performance Bottlenecks and other outstanding items Identify and establish Performance/functional outliners and any other outstanding items Todd S/Jeff O 29th June
I4 Review & Sign-off above milestones Review and Sign-off on the above tasks. Todd S/Jeff O 30th June
I5 Review next Iteration Plan Review the plan for the next iteration including tasks, timelines Todd S/Jeff O 30th June

Final Iteration

TimeLine: Begin: 1st July 2009 - End: 31st July 2009

ID Name Description Status Assigned Start Date End Date Dependency Notes
M1 Code Merge Merge code with Head and resolve conflicts. Jeff O 3rd July
I1 Scope Freeze Identify and freeze the set items identified for completion. Jeff O 3rd July
T1 Testing: User Acceptance Tests Complete the UAT -- which is part of the continuos iteration - this one should be the final pass Jeff O 10th July
T2 Testing: Pg Performance Benchmarks with fixes Execute and Establish the Pg Performance Benchmarks for the application. Tushar/Vikram/Jeff O 24th July
D1 Develop Guidelines for Database compatibility Develop a set of guidelines for the general Database compatibility for future enhancements to the product. Jeff O 24th July
D2 Develop Packaging Build the packaging for the application. Jeff O 24th July
D3 Develop Performance Bottlenecks Fine tune the application for the identified performances. Gurjeet/Vikram 17th July
M2 Final Code Merge Merge code with Head and resolve conflicts. Jeff O 27th July
T2 Testing:Package Test the end package Tushar/Vikram/Jeff O 31st July
I2 Review & Project Sign-off Review the above as well as sign-off for the project Completion Jeff O 3rd August