Remediation Tracker Template

github-actions[bot] edited this page Nov 29, 2026 · 1 revision

Last reviewed: 2026-11-29

Prerequisites: Templates index ยท Assessment findings lifecycle ยท Vulnerability finding template.

๐ŸŽฏ Purpose

A plan of action and milestones (POA&M) for the findings of one engagement, kept up to date until every item is closed or formally accepted.

โš™๏ธ Function

Records the four POA&M elements that NIST SP 800-115 cites from SP 800-37 (tasks, resources, milestones and scheduled completion dates), the SP 800-115 section 8.3 status of each item, its retest result and its SSVC decision. remediation-tracker.csv holds the same columns for spreadsheets and ticket imports.

๐Ÿ† Goal

Every item has one owner, an agreed date, a current status and a retest result, so the tracker can serve as what SP 800-115 section 8.2 calls a benchmark for tracking progress.

๐Ÿ“‹ When To Use

  • After the report is delivered, to plan remediation with the client.
  • At each status review, to update items as pending, partially accomplished or accomplished (SP 800-115 section 8.3).
  • When importing findings into a ticketing or findings platform.

๐Ÿงญ Tracker Rules

  • POA&M Status is pending, partially accomplished or accomplished. Retest Result is not retested, or one of the lifecycle's retest states: fixed, mitigated, accepted, still open or inconclusive. An accomplished item is not closed until it has been retested.
  • SSVC Decision is Track, Track*, Attend, Act or Not assessed. CISA describes Track as remediation "within standard update timelines", Attend as "sooner than standard update timelines" and Act as "as soon as possible". SSVC gives no day counts, so the scheduled date is agreed with the owner.
  • SP 800-115 section 8.3: test the fix in a replica environment where possible, get the system owner's approval through change control, then put the fix in place and verify it.
  • The CSV header is finding_id,asset,task,owner,resources,milestone,scheduled_completion,poam_status,retest_result,ssvc_decision,notes, one column for each column of the table below, in the same order. For later imports, build an idempotent key from engagement, asset and finding ID (lifecycle integration guardrails).

Canonical reference: Assessment findings lifecycle owns the import and retest workflow. This section is a summary.


๐Ÿ—‚๏ธ Tracker Record

Field Value
Engagement ID (engagement_id) {{engagement_id}}
Tracker owner (tracker_owner) {{tracker_owner}}
Last updated (last_updated_date) {{last_updated_date}}
CSV companion (csv_companion) {{csv_companion}}

๐Ÿ“‹ Remediation Items

Finding ID Asset Task Owner Resources Milestone Scheduled Completion POA&M Status Retest Result SSVC Decision Notes
{{item_finding_id}} {{item_asset}} {{item_task}} {{item_owner}} {{item_resources}} {{item_milestone}} {{item_scheduled_completion}} {{item_poam_status}} {{item_retest_result}} {{item_ssvc_decision}} {{item_notes}}

๐Ÿงพ Change Log

Date Change By
{{log_date}} {{log_change}} {{log_by}}

๐Ÿ“š Sources

See also

Related Files